SPCP-0322-03336
Case Study

St Pauls Church

Perth • Scotland

McIntyre Masonry Ltd was Haddens main subcontractor on this primarily stone and masonry contract in Perth’s city centre. The church has been sitting derelict for several years and required extensive restoration works. Perth City Council decided to crated an open air space. We carried out the stone work along with brick and render works.

Our work package included, 4no. pinnacles stripped and rebuilt, parapet course stripped and rebuilt, 12no. bartizans stripped and rebuilt, new arch voussoirs, ornate corners and other ornate stones, several structural alterations and stabilising works along with stripping and rebuilding the main spire. We imported around 60m3 of new sandstone shaped in our workshops.

Specification

Role

Specialist Sub-Contractor

Client

Hadden Group

Contract Value

£800,000